David W. Carter High School
This was part of a major building renovation. Remove existing PUF (foam roof) roof system, coal-tar pitch roof system down to the deck, install new tapered ISO insulation, raise all gas, electrical, plumbing lines, equipment curbs as needed. Install new Modified Bitumen “Cool Roof” and associated sheet metal, flashing and trim. Remove and replace old windows with new double pane windows.
Client
Dallas ISD
Project Type
Partial roof replacement
Project Location
Dallas, Texas
Project Size
103,500 square feet
Services Provided
Provide building envelope consulting services for partial roof replacement and window replacement.
Project Duration
75 days
Project Manager
Harold Stephens